Active Projects
Planned Major Projects
- Booster Station Replace/repair 2 pumps
. Pump 1 replacement initiated Jan 2026; completed 3/16/26
. Pump 2 replacement planned June 2026;; pump pulled for repair 6/22/26
- Update obsolete protocol convertor and data logger - work initiated late Jan 2026
- Booster Station update - work initiated late Jan 2026
- Install Neptune radio read meter on well #3; completed June 2026
- Replace Booster station flow meter
- Install 3 new Tosibox for SCADA fiber optic connection; 5/20/26 parts on hand
- Upgrade to Neptune radio read customer meters - ongoing throughout the year: 310 total meters; less then 100 remaining to be replaced as of 6/22/26
- Install more accurate water tank meter
- Well #1 Pump Motor Replacement - work initiated Jan 2026; completed 3/6/26
- Improve water filter automation - work initiated late Jan 2026; work completed Mar 2026
- Disposal of old toxic chemicals stored at water treatment plant: initiated May 2026;completed June 2026
- Precise mapping of District infrastructure: software and equipment approved June 2026
- Lift station power backup
- Lift Station Security Infrastructure
- upgrade Donala flow meter
Unscheduled 2026 Projects
- Leak repair viciniy 980 Tari Dr 3/6/26; completed 3/12/26
- Customer service line repair and main valve replacement vicinity 955 Tari Dr: completed 5/27/26
ADA Accessible Web Site
The District activated this new website in September 2024 which is ADA compliant. All pages and documents in the new site have been checked for accesibility.
Upgrade to remote read meters
As older meters stop working they are being replaced with remote read meters. The District is looking to accelerate meter replacements, particularly for those properties with difficult to access meters.

Infrastructure mapping
The district delivery and wastewater system was not adequatly mapped when it was developed back in the 1960s. The District is acquiring GPS mapping equipment and mapping software to precisely document locations of service lines, valves, fire hydrants and curb stops.
Water Treatment Plant Display Panel
The display panel at the plantwas almost 30 years old and was identified as being antiquated and presented a risk to continued operations. The District has replaced the panel with a state of the art touch screenHuman Machine Interface (HMI) panel.


Refurbish Water Filters at the Treatment Plant
The treatment plant has two large water filters; the District refurbished one of those filters in 2024 and the other in 2025. Work started on the first filter December 13, 2024 and the second filter was completed mid-2025






Lift Station backup generator
When there is a power outage our lift station shuts down and waste water overflows into a retention pond. A few years ago during a 4 day outage that pond almost overflowed before power was restored. We have reviewed bids for acquisition, installation, and periodic maintenance of a backup generator to automatically power the lift station during such outages. Refurbishing the second water filter is a priority; if the 2025 budget allows, the District will start work to acquire the backup generator.
Periodic flushing of the water delivery system
Following a schedule, the District periodically opens fire hydrants to allow sediment to be flushed from the system.
Periodic flushing and video taping of sections of the sewer system
Based on video review, repairs to the sewer system are completed as necessary.
Curb Stop Locations
The District recently spent a couple years locating curb stops (the valve to turn off water supply to the house). We have not been able to locate stops for approximately 30 homes because they have been covered by landscaping or driveways.


